09/2005

04/2007

Design

03/2007

12/2007

Site Preparation - Excavation and Foundations

01/2008

02/2008

Construction - Mobilization for Steel

02/2008

10/2008

Construction - Structural Steel Erection

10/2008

10/2009

Construction - Concrete, MEP Rough In

03/2009

10/2009

Construction - Curtain Wall / Exterior Facade

09/2009

08/2010

Construction - Fit Out / Interiors

02/2010

09/2010

Move-In / Commissioning / Turnover